Watkins-Spanish Lake Sanitary Relief
This project illustrates I&L’s Sanitary Sewer design experience. I&L was retained by the Metropolitan St. Louis Sewer District (MSD) to upgrade part of the Watkins-Spanish sanitary sewer network. This project replaced approximately 2,335 feet of 18-inch to 24-inch diameter sewers. The northern half of the project is located in St. Louis County’s Spanish Lake Park and the southern half is through a residential neighborhood consisting of quarter-acre lots. The existing sanitary system was comprised of a range of materials including reinforced concrete pipe, ductile iron pipe, vitrified clay pipe, and polyvinyl chloride pipe. Some reaches have been rehabilitated and are CIPP lined.
The scope of services includes the Alignment Recommendations Technical Memorandum, permitting, easements, Final Design, and bidding documents. The alignment study recommended replacing the existing system with 11 line segments and 2,327 linear feat of 27-inch sewer line. The design included coordination with St. Louis County Parks and MSD to minimize threats to existing features, recent improvements, and the lake. The coordination, design, and easement layout was a point of emphasis on this project due to deep sewers within Spanish Lake Park.
Right-Of-Way (ROW) and easement have recently finished for this project with I&L supporting MSD staff as requested. FInal Plans and bidding documents have been prepared for the District and Construction is ongoing as of 2025.
Project Details
Key Personnel:
- Tim Dean, PE, LEED AP, CFM
- Matt Auld, PE, ENV SP
- Mark Meyer, PE, CFM
- Jenna Stombaugh, EI
Project Features:
- Sanitary Sewer design
- New Alignment
- Capacity Improvement
- Alternatives TM
- Permitting
- ROW and Easements
- Final Plans and Specifications
- Construction Cost Estimate
- Public Involvement
Year:
- Design: 2020-2024
- Construction: Ongoing
Team:
- I&L, Sabur, Millennia