Water & Sewer Main Improvements Projects (Multi-Site)
This project illustrates I&L’s water and sanitary sewer main connection and design experience. The City of St. Charles, MO retained I&L to design large-scale water main connections and sanitary sewer alignment as part of stream stabilization and capacity improvement projects along Boschert Creek and Crystal Springs Creek. The projects included 5 locations, plans in AutoCAD Civil 3D, quantities, costs, permitting, and specifications.
Sanitary Sewer & Stabilization
The design included 2,500 feet of sanitary sewer main alignment as well as 2,600 feet of channel stabilization.
Water Line
The design included approximately 2,000 feet of new 8-inch water main to connect the existing 6-inch water main along San Juan Drive to the existing 16-inch water main along South River Road, and to connect three existing 6-inch water mains on Le Chateaux Court, Ridgeview Drive, and West Randolph Street.
Final water line design and replacement included upsizing approximately 300 feet of 6-inch water main along San Juan Drive plus approximately 1,330 feet of new alignment 8-inch water main near Le Chateaux Court.
Services included Field Site Walkthrough, alternatives analysis, new alignment, surveying, preliminary design-plans and cost, public engagement including meetings with affected residents, permitting, utility coordination, Right-of-Way plans, Easements documents and legal descriptions, Pre-Final PS&E, Final PS&E, and Approved Documents.
Project Details
Key Personnel:
- Matt Auld, PE, ENV SP
- Tim Dean, PE, LEED AP, CFM
- Mark Meyer, PE, CFM
- Jenna Stombaugh, EI
Project Features:
- Water Main
- Sanitary Sewer
- Utilities Connection
- New Alignment
- Multi-Site
- Bank Stabilization
- Permitting
- Easements and ROW Documents
- Final Plans, Specifications
- Construction Cost Estimate
- Public Involvement
Year:
- Design: 2019-2020
- Construction: 2021-2022